Note that if the values of ABL DataSlot objects associated with a
Task object have been changed, the new values are
not sent to the Business Process Server when
Reassign( ) is called. For example, if a developer gets a
Task object, changes the values of some of its
DataSlots, calls
Reassign( ) on the
Task, and then gets the
Task from the server again, the
DataSlot values will not reflect the changes that had were previously made locally to the ABL
DataSlot objects. Values in ABL
DataSlot objects are not updated until
Complete( ) is called on the
Task.